Thursday, April 18, 2019

Welcome to a very busy Easter weekend edition of GasNewsOnline.com!  There are a host of critical notices from several of the country’s interstate natural gas pipeline companies about issues relating to changes in pipeline operating conditions. 

Plus, we’ll also update you on the latest publicly released news of the day and provide the first glimpse of May’s expected temperatures from the National Weather Service, too.  

********************

Working natural gas in storage was 1.247 Tcf as of Friday, April 12, 2019, according to US Energy Information Administration estimates. This represents a net increase of 92 Bcf (which was 5 Bcf greater than analyst estimates). 

Natural gas stocks were 414 Bcf (or 26%) below the five-year average for the same week. 

On the NYMEX, the May, 2019 natural gas futures price reacted to the news and was down about three cents on Thursday at approximately $2.49/MMBtu.   Natural gas prices declined to their lowest level in nearly three years due to a seasonal lull in heating and cooling demand combined with surging gas supplies. 

It is interesting to note that not a single month of today’s NYMEX natural gas futures strip (through April, 2021) showed a natural gas price above $3.00/MMBtu.

********************

During today’s quarterly earnings release and conference call, Kinder Morgan provided an update on a few natural gas pipeline projects currently in progress:

In the Permian area, construction continues on the Gulf Coast Express Pipeline (GCX) project. The remaining 40 miles of the 36-inch Midland lateral was placed in service at the beginning of April 2019. Construction is progressing well on the 42-inch mainline and compressor stations associated with the project, which remains on schedule for a full in-service date of October 2019.

The approximately $1.75 billion project is designed to transport about 2.0 Bcf/d of natural gas from the Permian Basin to the Agua Dulce, Texas area, and is fully subscribed under long-term, binding agreements.

Progress also continues on the Permian Highway Pipeline (PHP) project . The civil and environmental surveys are substantially complete, and the land acquisition process is underway.

The approximately $2 billion PHP Project is designed to transport up to 2.1 Bcf/d of natural gas through approximately 430 miles of 42-inch pipeline from the Waha, Texas area to the U.S. Gulf Coast and Mexico markets and is expected to be in service in October 2020, pending regulatory approvals.

On the East Coast, the first of ten liquefaction units of the nearly $2 billion Elba Liquefaction Project is expected to be placed in service by approximately May 1, 2019. The remaining nine units are expected to be placed in service sequentially, one per month thereafter.

The federally approved project at the existing Southern LNG Company facility at Elba Island near Savannah, Georgia, will have a total liquefaction capacity of approximately 2.5 million tonnes per year of LNG, equivalent to approximately 350 million cubic feet per day of natural gas.

********************

In summary, many interstate natural gas pipelines have posted critical notices to shippers requiring that they do not create pipeline imbalances caused by lack of market demand during the upcoming Easter holiday weekend.  Let’s review… 

Algonquin Gas Transmission:

Algonquin Gas Transmission (AGT) has limited operational flexibility to manage imbalances. Effective 9:00 AM CCT, Friday, April 19, 2019, AGT requires all delivery point operators keep actual daily takes out of the system equal to or greater than scheduled quantities regardless of their cumulative imbalance position unless otherwise coordinated with your operations account representative.

All receipt point operators are required to keep actual daily receipts into the system equal to or less than scheduled quantities regardless of their cumulative imbalance position unless otherwise coordinated with your operations account representative.

ANR Pipeline:

Southwest Mainline Capacity Reduction (Posted 4/18/19)

ANR will begin planned maintenance at the Havensville compressor station between April 29 and May 2.  The total SWML Northbound (LOC#226630) capacity will be reduced by the following:

90-MMcf/d (leaving 600-MMcf/d available) 4/29 – 5/2

Based on current nominations through the SWML, it is anticipated that this posting will result in the capacity allocation reduction of IT and Firm Secondary volumes.

Also from ANR:

SW Area Capacity Restriction (Posted 4/18/19)

From April 29th through May 4th, ANR will perform planned pipeline maintenance between its E.G. Hill and Gageby Compressor Stations in the Southwest Area (Zone 4). As a result, ANR will shut-in the Beaver-CIG (REC FR CIG) receipt point, DRN #16435.

The total E.G. Hill from Gageby (LOC #226643) capacity will be reduced by the following:

50-MMcf/d (leaving 175-MMcf/d available) 4/29 – 5/4

Based on current nominations, it is anticipated the above reductions will result in the curtailment of nominations associated with IT and Firm Catalog Receipt points in the affected area.  Also, interconnects along this segment may experience higher line pressures.

Colorado Interstate Gas (CIG):

In response to continuing and prolific natural gas production growth in the Denver-Julesburg Basin – and the mounting market need for timely transportation capacity – Colorado Interstate Gas Company, L.L.C. (CIG) is conducting a binding Open Season for additional firm capacity to be made available by approximately November 1, 2019.  The additional transportation capacity offered in this Open Season will have primary receipt rights into CIG’s 5C Line north of a proposed new interconnection (“High Five Meter Station”) with CIG’s High Plains Lateral to be constructed at approximately milepost 29, and will have primary delivery rights at the High Five Meter Station of the CIG 5C Line and the Wyoming Interstate Company, L.L.C. (“WIC”) facilities at Bowie. 

For more details, please check the CIG Electronic Bulletin Board.  The posting is dated April 18, 2019.

This binding Open Season will commence today (April 18, 2019) and is scheduled to close at 10:00 a.m. Mountain Time on May 8, 2019.  CIG intends to provide notification of capacity awards by 5:00 p.m. Mountain Time on May 9, 2019.

Questions concerning this Open Season should be directed to:  Greg Ruben (713-520-4870) or Laine Lobban (719-520-4344). 

Columbia Gas Transmission:

Columbia Gas Transmission, LLC (TCO) reminds customers of a station power outage at the Cobb Compressor Station scheduled for Saturday, April 27, 2019 through Sunday, April 28, 2019.   

Due to this maintenance, the below internal constraints will be set to Zero Total Capacity.  All production will be shut-in with the exception of a limited quantity that may be needed to serve localized markets. 

Cobb South MA18 (A03SOUTH)

Cobb Northeast MA18 (A03NORTH)

Cobb Northwest MA18 (A03LOW)

Cobb Line H (A03LINEH)

Cobb CS MA18 (COBBA03) 

East Tennessee Natural Gas:

Boyds Creek Compressor Station Outage – April 23 – 24

ETNG will be conducting a compressor station outage at its Boyds Creek Compressor Station (Boyds) on the 3300 line. During this outage, west to east capacity through Boyds will be reduced to approximately 80,000 Dth per day.

Based on historical nominations, restrictions may be required for interruptible and secondary services and potentially primary firm services.

Enable Gas Transmission:

This Operational Alert is being issued pursuant to Section 20, GT&C, of EGT’s Tariff to advise shippers system wide that they will be required to maintain actual receipts and deliveries commensurate with scheduled volumes, beginning on Friday, April 19, 2019 at 9:00 A.M. and continuing until further notice.

Due to limited storage capacity, EGT anticipates it may be unable to support imbalance positions and may reduce scheduled quantities intraday to balance actual receipts and deliveries necessary to maintain system deliverability and operational integrity.

The availability of balancing and non-ratable services will be limited.  Hourly non-ratable nominations, as well as the use of imbalance positions must be pre-approved or within the posted limits on EGT s Daily Operating Plan. EGT will continue to monitor the pipeline s pressure and imbalances and will, if necessary, take further actions, including the issuance of one or more Operational Flow Orders (OFO).

EGT will schedule receipts and deliveries in accordance with EGT s Tariff.  This Operational Alert will remain in effect until further notice and will be updated as more information becomes available.

Gas Transmission Northwest (GTN):

May 2019- GTN Fuel and Line Loss Percentage

Pursuant to Gas Transmission Northwest’s (GTN) Tariffed Fuel Adjustments Provision, for the period of May 01, 2019 through May 31, 2019, a fuel usage rate of 0.0021% per Dth/mile will be in effect.

This percentage is inclusive of GTN’s current fuel and line loss surcharge of 0.0000% per Dth per pipeline mile, which is in effect through December 31, 2019, in accordance with GTN’s approved tariff provision, “Adjustment Mechanism for Fuel, Line Loss, and Other Unaccounted For Gas.”

Gulf South Pipeline:

Index 818 I.L.I. Pig Run – Begins April 23, 2019 – Ends April 24, 2019

Expansion Area 19 (Mississippi) Delivery Scheduling Group.- Capacity could be impacted by as much as 300,000 dth/d for the duration of the maintenance.  Please contact your customer service representative if you have any questions.

Kinder Morgan Louisiana Pipeline (KMLP):

SEGMENT 140 – MLV #7 – AT OPERATING CAPACITY 

Effective for gas day Friday, April 19, 2019, Timely Cycle, and continuing until further notice, KMLP is at operating capacity for gas going southbound through Segment 140, located in Jefferson Davis Parish, Louisiana.  AOR/ITS and Secondary out-of-path Firm transports are at risk of not being fully scheduled. 

Mississippi River Transmission (MRT):

Due to the potential negative impact of significant shipper long imbalance positions on MRT storage withdrawal operations, MRT is issuing a System Protection Warning (SPW) effective 9:00 a.m. Thursday, April 18, 2019, and continuing until further notice.

During this time:

1) Shippers should avoid daily long imbalance positions

2) MRT may not schedule any nominations that result in a daily long position.

3) MRT may not accept any makeup of short positions

4) MRT may not schedule nominations that result in counter-seasonal injection.

Failure to comply with this SPW may result in the issuance of an OFO.  Nominations will be confirmed and scheduled in accordance with MRT s Tariff.

Southern Natural Gas:

Based on the current milder weather forecast and projected demand on Southern’s system for the Holiday weekend, we are implementing an OFO Type 6 for long imbalances on Southern’s contiguous pipeline system effective for the start of the gas day, Friday, April 19, 2019, and until further notice. In order to maintain the operational integrity of Southern’s system, it is essential that Shippers and Poolers remain in balance (including their available no-notice injection entitlements).

The OFO Type 6 order will subject each Shipper/Pooler to the following tiered imbalance penalties:

Daily Imbalance Penalty
(Percent of Allocated Deliveries ) ( Per Dth )

0 – 2% or < 200 dth No Penalty
> 2 – 5% $1.00
> 5 – 8% $ 5.00
> 8% $15.00

Since the projected operational conditions are affected by receipts exceeding deliveries, the penalty will apply only to each Shipper/Pooler that has a net long imbalance (i.e., the party’s total allocated receipts exceed total allocated deliveries including available no-notice storage injections).

Tennessee Gas Pipeline:

OFO DAILY CRITICAL DAY 1 FOR ALL OF ZONES L, 1, 2, 3, 4, 5 AND 6 EFFECTIVE 4-19-19 

Due to forecasted milder weather, storage fields on test and anticipated lower demand for the holiday weekend, effective for the Gas Day of Friday, April 19, 2019, and until further notice, Tennessee Gas Pipeline, L.L.C.  (“Tennessee”) is implementing an OFO Daily Critical Day 1 for all of Zones L, 1, 2, 3, 4, 5 and 6 for all Balancing Parties (including LMS-PA, SA contracts acting as balancing parties, LMS-MA, and LMS-PL balancing parties).  This action is pursuant to Article X, Section 4 of the General Terms and Conditions of Tennessee’s FERC Gas Tariff.  

All delivery point operators in all of Zones L, 1, 2, 3, 4, 5 and 6 are required to keep actual daily takes out of the system equal to or greater than scheduled quantities regardless of their cumulative imbalance position.  All receipt point operators in all of Zones L, 1, 2, 3, 4, 5 and 6 are required to keep actual daily receipts into the system equal to or less than scheduled quantities regardless of their cumulative imbalance position.  In addition, it is essential that delivery point operators schedule gas at meters commensurate with takes within the affected areas.  All LMS-PA, SA contracts acting as balancing parties, LMS-MA and LMS-PL Balancing Parties are required to maintain an actual daily flow rate not exceeding 2% of scheduled quantities or 500 dths, whichever is greater for over-deliveries into the system and under-takes from the system. Customers will be assessed a rate of $5.00 plus the applicable Regional Daily Spot Price per dekatherm for that portion of physical quantities related to over-deliveries by receipt point operators and under-takes by delivery point operators which exceed this tolerance. 

THIS DAILY OFO CRITICAL DAY 1 WILL REMAIN IN EFFECT UNTIL FURTHER NOTICE. TENNESSEE WILL INFORM CUSTOMERS BY EBB WHEN THIS OFO WILL BE LIFTED.

Trailblazer Pipeline Company:

TRAILBLAZER MECHANICAL ISSUE–COMPRESSOR STATION 603–UPDATE #1

Trailblazer Pipeline Company LLC (“Trailblazer”) identified a mechanical issue with one of the two compressor units at Compressor Station 603. The unit is currently unavailable and is not expected to be available until late May, 2019. 

At this time, secondary firm quantities, as well as ITS/AOR are at risk of not being scheduled. Trailblazer will post updates as additional information becomes available.  For questions, please call your Account Director or Scheduling Representative.

Transcontinental Gas Pipe Line Company (Transco):

Transco recently provided notice of limited flexibility to manage imbalances and recommended shippers maintain a concurrent balance of receipts and deliveries. In order to ensure system integrity, maintain safe operations, manage imbalances, and handle within-the-day volatility, Transco is issuing an Imbalance Operational Flow Order (OFO).

Effective:        Friday, April 19, 2018

Ends:               Until Further Notice

Transactions:  Deliveries

Type:               Due to Shipper

OFO Area(s):  Zones 4, 5, and 6

Tolerance:        10% (or 1000 dth, whichever is greater)

This OFO is directed to shippers consistent with Section 52 of Transco’s FERC Gas Tariff General Terms and Conditions with a minimum of $50 per dth per day penalty.  This OFO will continue until further notice.  Buyers with imbalances greater than allowed tolerance will be subject to penalties specified in Section 52 of Transco’s FERC Gas Tariff General Terms and Conditions.

********************

The National Weather Service has published their first glimpse at the temperature forecast from the month of May.  It shows that the East and West coast areas could see above normal temperatures next month, while the majority of the midsection of the US is predicted to have normal to slightly below seasonal temperatures during the month of May.

That’s a wrap for this Thursday edition of GasNewsOnline.com.  We’ll return on Monday to provide an update on pipeline conditions and the latest energy news. 

Remember that our companion audio podcast is available via Apple Podcasts.  Subscribe today – it’s FREE

Happy Easter!

Edition 26 – Thursday, December 27, 2018

Welcome back to GasNewsOnline.com for Thursday, December 27, 2018.  The New Year is right around the corner, so we will check out the latest natural gas news and gas pipeline information which may affect your business through early next week.  All for FREE!

January’s natural gas futures contract looks to be up ten cents today and near $3.64/MMBtu for the new month at the Henry Hub in Louisiana.

From the US Energy Information Administration’s  Natural Gas Weekly report:

The natural gas plant liquids composite price at Mont Belvieu, Texas, fell by 52¢/MMBtu, averaging $6.21/MMBtu for the week ending December 19. The price of natural gasoline, ethane, propane, butane, and isobutane all fell for that reporting week.

According to Baker Hughes, for the week ending Tuesday, December 11, the natural gas rig count remained flat at 198. The number of oil-directed rigs fell by 4 to 873. The total rig count decreased by 4, and it now stands at 1,071.

********************

Let’s check out the latest postings from the electronic bulletin boards of the major interstate gas pipeline companies around the United States:

Algonquin Gas Transmission:

AGT Operational Flow Order


In order to maintain the operational integrity of the system, Algonquin Gas Transmission, LLC (AGT) is issuing an Operational Flow Order (OFO) pursuant to Section 26 of the General Terms and Conditions of AGT’s FERC Gas Tariff effective 9:00 AM CCT, December 29, 2018, to all parties, with the exception of those Operational Balancing Agreements required by FERC regulations, on the AGT system. 

This OFO does not affect the ability of AGT to receive or deliver quantities of gas for scheduled nominations to any customer or pipeline.

During the effectiveness of this OFO, all parties must be balanced such that actual deliveries of gas out of the system must be equal to or less than scheduled deliveries. The penalty shall apply to each dekatherm of actual delivery quantities that exceeds the greater of 4,000 Dth or 104% of scheduled delivery quantities. The penalty will be equal to three times the daily Platts Gas Daily “Daily Price Survey” posting for the High Common price for “Algonquin, city-gates” for the day on which such violation occurred as indicated in AGT’s General Terms and Conditions Section 26.8. In addition, AGT will not permit retroactive nominations to avoid an OFO penalty.

AGT may be required to issue an hourly OFO pursuant to General Terms and Conditions Section 26.7(d) to impose further restrictions in order to maintain the operational integrity of the system.

As previously posted AGT, requests that customers/point operators on AGT be aware of the impact non-ratable hourly takes from the system may have in causing delivery pressures reaching lower than desired levels. As a reminder, AGT’s system is not designed to sustain delivery pressures above contract levels while making non-ratable/accelerated deliveries above scheduled quantities for more than 6 consecutive hours, to be followed by flows below scheduled quantity for the balance of any 24 hour period. 

Furthermore, if customers/point operators don’t manage hourly takes from the system, 1) delivery pressures will be impacted and /or 2) AGT may be required to impose further restrictions or courses of action in order to maintain the operational integrity of the system.

This OFO will remain in effect until further notice.

East Tennessee Natural Gas:

Line 3100 Outage Update (5)

East Tennessee Natural Gas, LLC (ETNG) is providing the following update on its progress in returning to service the 3100 Line near its Dixon Spring compressor station. As posted on December 21, 2018, ETNG is working diligently to return the capacity thru Dixon Springs to approximately 300,000 Dth/d. The updated progress report is as follows: 

Progress Report: ETNG continues to be diligent on the three major construction activity work streams required to return the pipeline back to service. The three major work streams are: (1) Testing and installing new section of pipeline, (2) Installing temporary pig launchers/receivers and cleaning of the pipeline around incident location and (3) Removing temporary pig launcher/receivers and returning pipeline to service. 

As of December 26, 2018, the testing and installation of the new section of pipeline has been completed. As previously posted, ETNG has commenced and continues its pigging operations to clean the pipeline around the incident location. ETNG is projecting the final pig runs and other commissioning activities, such as the purging and packing of the system, to be completed on December 29th. There are various factors that could potentially change the projected return to service date, such as, but not limited to: weather conditions and unforeseen events due to existing pipeline conditions that could lengthen the work schedule. Based on the current schedule and progress made to date, ETNG is now projecting returning to service approximately 300,000 Dth/d of capacity thru Dixon Spring on DECEMBER 30, 2018.

Looking Ahead: ETNG will continue to provide updates on its progress until the 3100 line has been restored to full capacity. ETNG is committed to prioritizing the work in a safe and efficient manner in order to increase system capacity as quickly as feasible. 

El Paso Natural Gas:

Pipeline Conditions – Increasing Linepack in Advance of Weather

EPNG is concerned about the winter weather forecast to move into the Permian and San Juan basins Friday afternoon into Saturday morning and the potential for a loss of supply due to freeze offs. EPNG will be maintaining higher linepack until the winter weather moves out of the supply basins. Drafting of the system will undermine EPNG’s ability to increase and maintain linepack in advance of the potential supply underperformance.

Delivery point operators are encouraged to review their scheduled supplies to ensure that they are aligned with their flowing quantities.

Supply operators are encouraged to maintain their deliveries into the EPNG system at their scheduled rates.

Underperformance caps will be placed on non-performing supplies.

Imbalance payback off the system, such as Make-Up Delivery (MD) transactions, may be limited or denied due to operational concerns related to maintaining adequate linepack.

Kinder Morgan Louisiana Pipeline (KMLP):

FORCE MAJEURE – COMPRESSOR STATION 760 – LIFTED

KMLP has completed repairs at Compressor Station 760 in Acadia Parish, Louisiana (CS 760).  Therefore, effective for gas day Thursday, December 27, 2018, Intraday 1 Cycle and continuing thereafter, the force majeure will be lifted and flow will resume to normal operations.  All transport services are available.

Mississippi River Transmission (MRT):

MAIN LINE UTILIZATION SPW

Due to the potential for maximum utilization of northbound firm Main Line capacity causing a potential supply deficiency in the Market Zone, MRT is issuing a System Protection Warning (SPW) effective 9:00 a.m. Saturday, December 29, 2018 and continuing until further notice.

 During this time:

 1)           MRT may not schedule any IT or AOR volumes for delivery north of Glendale.

 2)           Firm volumes may be limited to their primary direction of flow on the system north of Glendale.

 3)           MRT may not schedule volumes that result in a daily short position in either the Market or Field Zones.

 4)           The use of imbalance positions may not be scheduled.

 5)           Pool transfers will not be permitted from MRT s Field Zone to its Market Zone.

 6)           Customers with primary delivery points in the Field Zone north of the Glendale Compressor station and a receipt point that utilizes South to North transportation, will be required to nominate and source all, or a portion of, their total nomination at primary receipt points and/or at available Market Zone supply locations, not to exceed applicable maximum receipt point quantities in order to support their primary deliveries.

 7)           Shippers whose firm transportation contracts have Texas Gas Boardwalk ( Boardwalk ) and/or EGT Olyphant ( Olyphant ) and/or Noark listed as primary receipt points, must schedule the full amount of their primary receipt point quantity each of those points or, if the primary receipt point is Boardwalk and/or Olyphant, at an alternative Main Line receipt point that is north of their primary receipt point (Olyphant and/or Noark) if they desire to fully utilize their contract MDQ. Shippers may elect to forego nominating their full primary receipt point quantity at any/all of these points, however, such shipper’s maximum scheduled and confirmed contract quantity shall be limited to their contract MDQ less any primary receipt point quantity at Boardwalk and/or Olyphant and/or Noark that is not scheduled and confirmed.

Shippers whose deliveries are affected by any of the Seven (7) conditions above are encouraged to source supply at their primary receipt points, MRT’s East Line, MoGas, or reduce applicable delivery volumes.

Failure to comply with this SPW may result in Customers being issued an individual OFO.  Nominations will be confirmed and scheduled in accordance with MRT s Tariff.

Natural Gas Pipeline Company of America (NGPL):

SEGMENT 11 – CS 104 – FORCE MAJEURE

Natural is experiencing electrical issues at Compressor Station 104 (CS 104), located in Barton County, Kansas (Segment 11 of Natural’s Midcontinent Zone).  As a result, Natural is required to reduce the maximum operating capacity through CS 104.  This is a Force Majeure event that limits Natural’s throughput capacity northbound through CS 104. 

The scheduling constraint will be at CS 104; therefore, any gas received south of CS 104 for delivery north of CS 104 will be impacted for the duration of this outage.  For scheduling purposes, the Midcontinent Pool (LOC 25078) is located south (upstream) of the constraint.  Additionally, firm transportation nominated from receipt points south of CS 104 (including the Midcontinent Pool) and transports associated with withdrawals from all Amarillo Storage points will be impacted.  Receipt points north of CS 104 will not be impacted.    

As such, effective for gas day, Friday, December 28, 2018, Timely Cycle and anticipated to continue until further notice,Natural will schedule Primary Firm and Secondary in-path Firm transports to no less than 75% of contract MDQ through CS 104.  Actual nomination levels and changes in pipeline conditions could result in changes to the percentages scheduled (lower or higher) on subsequent gas days.  AOR/ITS and Secondary out-of-path Firm transports continue to not be available.

The stated scheduling percentage is based upon the current level of firm capacity contracted for during this outage and is subject to change based upon operational conditions and Shipper utilization.  Permian Zone delivery points will be available as an alternative.  The Trailblazer Gage (LOC 902900), Rex Jefferson (LOC 42499), and Northern Border Harper (LOC 908090) receipt points, as well as other supply points downstream of this constraint will also be available.

Southern Star Central Gas Pipeline:

Winter Weather Advisory – Effective December 28, 2018 Cold weather is being forecasted across much of the Southern Star system beginning Friday, December 28, 2018, through Sunday, December 30, 2018. Southern Star is issuing a weather advisory effective gas day Friday, December 28, 2018, and requests that operators and shippers monitor weather conditions and ensure their business plans consider the temperatures forecasted. Southern Star will issue underperformance notices to each point operator not delivering the scheduled quantities they had confirmed. Southern Star will unilaterally reduce scheduled quantities per the tariff to match actual flow if the delivering operator does not remedy the underperformance in accordance with the notice.

Transwestern Pipeline Company:

12/26/18

Pipeline Conditions – Low Line Pack – Cold Weather

Transwestern is working to maintain and/or increase current line pack. This notice is due to cold weather moving into the Permian and the San Juan basins this week.

Customers are encouraged to review their transport to ensure that their flowing quantities are aligned with their scheduled supplies and to ensure their scheduled supplies are performing as expected.

Correspondingly, Transwestern plans to issue Underperformance Cut Notices to Receipt Point Operators that are flowing less gas into Transwestern than scheduled.

Any such UPR cuts will be handled by separate notices.

No Make-Up Deliveries or over burns due to operational concerns related to
maintaining adequate line pack.

If you have any questions, please contact Gas Control or your Marketing
Representative.

********************

Taking a look ahead to temperatures in the first week of January, the National Weather Service six-to-ten day forecast shows below average temperatures across much of the Midwest and Mid-continent regions with normal temperatures across the Great Lakes and Northeast.   The West Coast and Southeast may see slightly warmer temperatures than average.

Thank you for reading GasNewsOnline.com! Have a safe weekend, and a HAPPY NEW YEAR!

Edition 23 – Thursday, December 13, 2018

Welcome back to GasNewsOnline.com!   We hope to give you a little holiday cheer with publicly available news and information about the natural gas business and a glimpse of warmer weather in the extended forecast for the week of Christmas.

First, let’s take a look at what is making news in the energy business:

The US Energy Information Administration published their weekly natural gas storage report today.  Below is a summary of the report:

EIA Natural Gas Storage Data
Total (12/07/18): 2,914 Bcf
Total (11/30/18): 2,991 Bcf
Net change: -77 Bcf
Year ago stocks: 3,636 Bcf
% change from year ago: -19.9
% 5-year avg stocks: 3,637 Bcf
% change from 5-year avg: -19.9 %

Cheniere Energy, Inc. announced Wednesday that the first commissioning cargo of liquefied natural gas (LNG) has loaded and departed from its Corpus Christi liquefaction facility in Texas, marking the first export of LNG from the state and from a greenfield liquefaction facility in the lower 48 states. The LNG was loaded on the LNG carrier Maria Energy, chartered by Cheniere Marketing, LLP.

“Exporting the first commissioning cargo of LNG from Texas demonstrates Cheniere’s ability to deliver projects safely and ahead of schedule, including the first greenfield LNG export facility in the lower 48 states,” said Jack Fusco, Cheniere’s President and CEO. “This milestone further reinforces Cheniere’s position as the leader in U.S. LNG, with a world-scale liquefaction platform that provides significant competitive advantages as we continue to execute on our growth strategy.” 

The Corpus Christi liquefaction facility consists of three large-scale LNG production units — or trains — and supporting infrastructure, with an additional seven smaller trains proposed.  The facility’s first train produced first LNG in November and is expected to reach substantial completion in the first quarter of 2019.  Train 2 is expected to reach substantial completion in the second half of 2019, and Train 3 in the second half of 2021. The facility will also feature three LNG storage tanks with capacity of approximately 10.1 billion cubic feet equivalent and two marine berths.

In other energy news:

Houston-based Parker Drilling Company announced Wednesday that it has entered into a restructuring support agreement (“RSA”) with holders of the Company’s securities.  To implement that agreement, Parker has voluntarily filed for Chapter 11 protection in the U.S. Bankruptcy Court for the Southern District of Texas.

The existing management team is expected to remain in place, and the Company expects to complete the restructuring process in the first quarter of 2019.

The Company anticipates that its cash flow and existing liquidity will be sufficient to support global operations during this period.   The proposed Plan, which is subject to Court approval, reduces approximately two-thirds of funded debt and injects $95 million of new equity capital.

“Our operational results have continued to improve this year, and we anticipate new opportunities for profitable growth across our drilling and rental tools businesses. The steps we are announcing today will ensure that we have the appropriate capital structure to take advantage of these opportunities to strategically grow our assets, our global footprint, and our suite of products and services,” said Gary Rich, Chairman, President and Chief Executive Officer.

********************

The interstate gas pipeline grid is shifting from an early winter mode of operation and providing the industry a brief chance to replenish storage levels as some warmer weather is upon us.  Let’s take a look at some of the critical postings:

ANR Pipeline:

SW Area Capacity Restriction

New: ANR will begin unplanned compressor maintenance at its Mooreland Compressor Station located in Woodward County, Oklahoma, in the Southwest Area (Zone 4).  During the period of December 13th, 2018 through January 13th, 2019, ANR Shippers can expect higher than normal pressures in the pipeline segment upstream of the Mooreland Compressor Station.

Dominion Energy Transmission:

Effective start of gas day, Friday, December 14, 2018, PL-1 restrictions will be lifted (supersedes Notice ID: 209910).

Additionally, Dominion is lifting capacity restrictions on its Northern, TL-400, and Oakford operating areas on Friday, December 14.

Dominion Energy Questar Pipeline:

In-line inspection results for JL47 indicate that remediation is necessary on a portion of the pipeline.  Dominion Energy Questar Pipeline (DEQP) has scheduled the repair for December 18, 2018.  To facilitate the work, Altamont MAP 145, Randlett Tap MAP 419, Pleasant Valley Tap MAP 413 and Brundage Mtn Tap MAP 144 will all need to be shut-in and nominations will not be accepted for cycles Timely through ID2 with volumes, returning to normal in cycle ID3.

East Tennessee Natural Gas:

ETNG Operational Flow Order – East of Boyds Creek — LIFTED

Effective today (Thursday, December 13), East Tennessee Natural Gas (ETNG) is lifting the Operational Flow Order for meters east of Boyds Creek issued on December 5, 2018.

ETNG has limited operational flexibility to manage imbalances. ETNG requires all delivery points located east of Boyds Creek to carefully review demand for gas and schedule gas consistent with daily needs and to tender and receive gas consistent with confirmed nominations regardless of their cumulative imbalance position unless otherwise coordinated with your operations account representative.

Additionally, ETNG requires all delivery points on its 3200 line located between Tracy City to Topside and on the 3500 line to keep actual daily takes out of the system equal to or less than scheduled quantities regardless of their cumulative imbalance position. All receipt point operators on the 3200 Line between Tracy City to Topside and on the 3500 line are required to keep actual receipts into the system equal to or greater than scheduled quantities regardless of their cumulative imbalance position.

El Paso Natural Gas:

The Force Majeure event that was declared on December 7, 2018 (Reference Critical Notice 603991) at Dimmitt Compressor Station will be lifted effective for Gas Day December 13, 2018 Cycle 3 (Intraday 1). The net capacity at AMAR N returns to 283,100 dekatherms consistent with El Paso Natural Gas Company’s December Maintenance Report (Reference latest Maintenance Notice 603975).

Enable Gas Transmission:

This Operational Alert is being issued pursuant to Section 20, GT&C, of EGT Tariff to notify shippers of planned maintenance at EGT’s Byars Lake Compressor Station.

Effective January 9, 2019, at 9:00 a.m. and continuing through January 10, 2019, EGT will conduct planned maintenance on its Byars Lake Compressor Station, located in McClain County, Oklahoma and in EGT’s West 2 Pooling Area.  During this maintenance, capacity through EGT’s Allen Compressor Station will be limited to approximately 780,000 Dth/d.  Point operators will experience higherpressure.

Based on current nominations, EGT expects impacts to its services, including potential impacts to firm service. During the planned maintenance, shippers whose receipts are in the West1 and West 2 pooling areas West of the Allen Compressor Station should nominate point to point in order to maintain the highest priority level of service.

Florida Gas Transmission:

FGT is performing planned pipeline maintenance upstream of FGT Compressor Station 10. This maintenance began on December 3, 2018 and is to be completed by the end of gas day December 21, 2018. During this maintenance FGT will schedule up to 1,100,000 MMBtu/day through Station 10. During normal operations, FGT schedules up to 1,300,000 MMBtu/day through Station 10.

FGT is performing maintenance on pipe near the FGT/Tennessee Carnes Interconnect (POI 10258). This maintenance began on December 3, 2018 and is to be completed by the end of gas day December 21, 2018. During this maintenance zero volumes will be scheduled at the FGT/Tennessee Interconnect. During normal operations, FGT schedules up to 60,000 MMBtu/day through the FGT/Tennessee Carnes Interconnect.

Kinder Morgan Louisiana Pipeline (KMLP):

Compression associated with the Sabine Pass Expansion Project, (Docket No. CP 17-22-00), is expected to go into service on December 13, 2018.  KMLP will begin assessing fuel gas on the “North to South Transportation Path” as defined in Section 1.30 of KMLP’s General Terms and Conditions. 

Effective December 13, 2018, the Fuel Gas Total Reimbursement Percentage will increase from 0.00% to 0.72%.  This percentage was approved by FERC on November 27,2018 in KMLP’s filing in Docket No. RP19-197-000.  The Unaccounted For Gas Total Reimbursement Percentage remains at 0.00%.  Shippers are advised to schedule quantities with the revised percentages. 

Natural Gas Pipeline Company of America (NGPL):

Natural has experienced horsepower issues on the Amarillo mainline at Compressor Station 103 (CS 103),located in Ford County, Kansas (Segment 11 of Natural’s Midcontinent Zone).  This is a Force Majeure event that will require Natural to reduce temporarily the maximum operating capacity northbound through CS 103 during this restriction. 

The scheduling constraint will be at CS 103; therefore, any gas received south of CS 103 for delivery north of CS 103 will be impacted. The Midcontinent Pool (PIN 25078) is located south (upstream) of the constraint.  Additionally,transports associated with storage withdrawals will be impacted. 

As such, effective for gas day Thursday, December 13, 2018, Timely Cycle, and anticipated to continue until further notice, Natural will schedule Primary Firm and Secondary in-path Firm transports to no less than 82% of contract MDQ through CS 103.  Actual nomination levels and changes in pipeline conditions could result in changes to the percentages scheduled (lower or higher).  AOR/ITS and Secondary out-of-path Firm transports continue to not be available during this event.   

Tennessee Gas Pipeline:

Effective for the Gas Day of Friday, December 14, 2018, and until further notice, Tennessee Gas Pipeline, LLC (“Tennessee”) is lifting the Daily Critical Day 1 OFO for all areas east of STA 219 on the 200 Line (including the Niagara Spur) and on the 300 Line.  However, it is imperative that customers continue to match physical flows with scheduled volumes in this area in order to avoid the issuance of any additional actions in these zones. 

Texas Eastern Transmission:

Texas Eastern Transmission (TE) has experienced an outage impacting capacity through its Bernville compressor station in Pennsylvania. This outage results in a capacity of approximately 2,947,000 Dth/d through the Bernville compressor station beginning on Gas Day December 14, 2018.  TE anticipates the outage will last for approximately 2-3days.

In addition…

Effective today (Thursday,December 13), Texas Eastern (TE) is lifting the Market Area Zone M3 Operational Flow Order effective on December 4, 2018.

As previously posted, TE has limited operational flexibility to manage imbalances. TE requires all delivery point operators in Market Area Zones M1-24, M2-24 and M3 to keep actual daily takes out of the system equal to or less than scheduled quantities regardless of their cumulative imbalance position unless otherwise coordinated with your operations account representative. All receipt point operators in Market Area Zones M1-24, M2-24 and M3 are required to keep actual daily receipts into the system equal to or greater than scheduled quantities regardless of their cumulative imbalance position unless otherwise coordinated with your operations account representative.

Additionally, TE requires all shippers and point operators in Access Area Zones STX, ETX, WLA and ELA and Market Area Zone M1-30 and M2-30 to carefully review demand for gas and schedule gas consistent with daily needs and to tender and receive gas consistent with confirmed nominations regardless of their cumulative imbalance position unless otherwise coordinated with your operations account representative.

Furthermore, due to impending colder weather, in order to maintain the operational integrity of the system TE is issuing an Operational Flow Order (OFO) pursuant to Section 4.3 of the General Terms and Conditions of TE’s FERC Gas Tariff effective 9:00AM CCT Monday, December 17, 2018 to all delivery parties, with the exception of those governed by a FERC gas tariff, in Texas Eastern’s Market Area Zone M3.

This OFO does not affect the ability of TE to receive or deliver quantities of gas for scheduled nominations to any customer or pipeline.

During the effectiveness of this OFO, all parties must be balanced such that actual deliveries of gas out of the system must be equal to or less than scheduled deliveries out of the system. The penalty shall apply to each dekatherm of actual delivery quantities that exceeds the greater of 2,000 Dth or 102% of scheduled delivery quantities. The penalty will be equal to three times the arithmetic average of daily Platts Gas Daily “Daily Price Survey” posting for the High Common price for the geographical region, as defined in Section 8.5(a) of the General Terms and Conditions of TE’s FERC Gas Tariff for the day on which such violation occurred. In addition, TE will not permit retroactive nominations to avoid an OFO penalty.

TE may be required to issue an hourly OFO pursuant to General Terms and Conditions Section 4.3(H) to impose further restrictions in order to maintain the operational integrity of the system.

********************

According to Santa’s friends at the National Weather Service, the eight-to-ten day temperature forecast is showing that most of the United States may see normal to above-average readings heading into Christmas!  Ho, Ho, Ho, indeed!

Enjoy a weekend of fewer operational flow orders on the pipelines for a change! 

Thanks for visiting GasNewsOnline.com!  Please tell a friend in the gas transportation and scheduling/trading business about us.  Our information is FREE!